Buildings: 9 Geschosse Wohngebaeude Ueberwachung

Case study:  System

Real-time monitoring during construction
Wall deformation during pouring

Project Description

Summary: Real time monitoring of the behaviour of an external wall of a building during pouring of reinforcement wall

Clients: gb&t Geb?debestand & Technik GmbH

Place: Sisseln (Switzerland)

Period: 2009  - 2009

Installation: Smartec

Structure's short description: 9 levels apartments building

Aim of monitoring: The building war renewed and consolidated

Number of sensor: 1

Main Results: The real-time measurement were taken continousely every 5 seconds during pouring of concrete (~45 min) and during the following 90 minutes. The measuring system was supposed to trigger a pre-warning in case of a wall deformation of 2mm and a warning in case of a 2.5mm deformations.

Monitored wall with sensor installation set-up

Sensor detail